Welcome to the Tenant Information Website!
This website provides information for tenants about the construction process of the new building on the St. Dennis property.
The new building is being constructed on a portion of the vacant land located on the east side of 7 St. Dennis.
Key Reminders:

As part of the construction of the new building, tenants can expect a series of permanent upgrades to 7 St. Dennis including:
Questions?

All notices and updates on the construction process will be made available here. Please check back regularly for the latest information.
Notice of Lobby Pop-up
This page provides details about the timeline for the construction process. As work progresses, additional information and updates will be shared.
We are here
Installation of safety and mitigation measures and relocation of existing driveway ramp
(Fall 2025 – Winter 2026)
New Building Construction
Excavation and drilling work for geothermal system and new building foundation
(Summer 2026— Winter 2027)
New Building Construction
Construction of the building
(Winter 2027— Summer 2028)
New Building Construction
Construction of new building interior, and landscaping improvements
(Summer 2028— Winter 2029)
New Building Construction
New residents move into building
(Spring 2029)
You will not have to move as a result of the proposed development. Your rent will not change as a result of the proposed development (increases through the Residential Tenancies Act will still apply). Tenants will be provided with updates throughout the construction process.
Yes. To accommodate the new building, the existing driveway entrance will be temporarily relocated west of its current location. The secondary entrance will be upgraded to serve as the temporary main entrance. The existing parking ramp will be permanently moved to the south side of the building. Tenants can also expect improvements to the landscaping around the building, the waste management facility, and accessibility features.
Your safety and comfort are our top priorities. We will adhere to all requirements and protocols set by the City of Toronto and the Province throughout the construction process. This includes installing fencing, hoarding, and gates around the construction area; managing construction vehicle movement; providing tenants with regular updates; and ensuring full compliance with all City and Provincial safety regulations.
As part of the construction process, we are required to prepare a Construction Management Plan, which has details and information about the mitigation plan for potential disruptors such as noise, dust, stormwater, erosion, and waste management. We invite you to contact a member of the project team if you have any specific questions.
Please do not hesitate to reach out to the Project Team using the contact form below. A member of the Construction Management Team will be happy to assist you shortly. Feel free to also call the following number should you require immediate assistance: 1-888-391-7528
Reach out to the team with your questions and comments on the construction process for the lands at St. Dennis. A member of the Construction Team will respond to you soon. If the matter is urgent, please call this number and a member of our team will assist you: 1-888-391-7528.